Wednesday, April 2, 2014

Successful audition notification letter


Hi (addressee),

We are pleased to inform you that you are successful following your
audition last week for a part in our short film, Castles in the Air.

I have attached a PDF copy of the script and you will be playing the
part of (specified role).  As of typing is most likely that we will be
filming on Friday, January 31st and possibly February 1st
if we need an extra day. Please confirm that you will be able to make
these dates.

Looking forward to working with you,

Enda

Rejection letter sent to all unsuccessful applicants post auditions

Dear (addressee),

Thank you for your audition last week for our short film. Unfortunately I have to tell you that you were not successful on this occasion. We were very impressed with your monologue and your improv, and we mean it when we say it was a particularly difficult decision choosing between everyone we saw for our two roles.

Our final decision really came down to selecting who we believed was the closest match to the characters as they are written in the script.

Myself and David certainly felt that we were very fortunate in terms of the amount of talent we saw in the auditions and In light of the above, we would love to keep you in mind for future projects if that is ok with you.

Again, thank you for attending the audition and we much-enjoyed going through the dramatic process with you.

Regards,

Enda 

Sunday, February 9, 2014

Evaluation of my role as a Producer during preproduction (First term)

When we began the Producer module it soon became clear to me that I was not totally aware of a Producer's full role during a film production.  As the term went on, I found it more and more interesting to learn just how thorough and organised a producer needs to be and I was unaware of just how much work they have to do, especially seeing as they act as the primary liaison for all teams on a production.  I also found it interesting to learn how important a producer's relationship is with the director.

I found some of the content in the class easy enough to understand and beneficial to know for future reference. This included learning how to colour mark a script, fill in break down sheets and how to adapt a script to a shooting script.  But I found some elements such as dividing script pages into 8ths, drawing up legal forms and how to correctly draw up a budget more difficult to understand.

My personal contribution to the Producer preproduction paperwork was to provide the script break down and draw up the production schedule.  I also found the locations.

Upon breaking down the script, the initial production process for Castles in the Air was not on the surface a particularly complicated one.  This was due to the relative simplicity of the main script requirements i.e. a total of three characters and a maximum of two locations. However it did have its challenges.

Firstly, we had a potentially difficult mock up scene ahead of us in that we would need to make somewhere look like a convincing hospital waiting room on screen.  We figured attempting to shoot in an actual waiting room would be far too troublesome in terms of schedule arrangement as well as noise levels.  Secondly we would have to get our hands on a full set of surgical scrubs and we had a difficult prop to get hold of with the memorial bench plaque.


As with the Director module, our first term phase of the preproduction process as Producers did not go well.  Again almost all of our documentation was either insufficiently drawn up, not provided our had gone missing in transit to the clip breakage. 


Looking back to find out where we went wrong, some of the same issues arise such as bad communication as Producers and not seeing each others documentation until the submission date. Personally I also found it a more difficult module to understand on the whole than Director.

I thought I had understood the script breakdown process better than I did.  I still think I would have difficulty dividing a script into 8ths, and it did not help that each script I used as an example did not fit into exact 8ths.  This leads me to believe that it is more a case of a know-how through practice than an exact numerical summation.

I also found the legal paperwork and budgeting hard to comprehend.  I do not feel I have enough of an understanding of basic legal speak to be able to draft a proper release form from scratch and I would find it hard to draft up a budget without having actual occurring costs.

However on the plus side, I do feel I was good at getting things organised.  I was always on the lookout for locations and I found both of the locations we were going to use.  I was also the one who looked into prop and costume research.

In conclusion, I would definitely need to have a greater understanding of the full set of tasks of a producer in order to have done better in the first term assignment.  Although I am, and have always been, the type of person who learns far better by actually doing than by following instruction.  So I have hope that the continued first hand experience of working on our film throughout the second term will strengthen my understanding of the roles and tasks of a producer.






Monday, February 3, 2014

Production Schedule - Castles in the Air


Castles in the Air Production Schedule (Second term)

Preproduction

Monday January 13th to Wednesday January 15th
Auditions 6 – 7pm in Coláiste Dhúlaigh & Library

Monday January 20th
Final decision on actors and email notifications

Tuesday January 21st
Sound test: 10am – 11am. Coolock Civic Centre

Production

Monday Jan 27th & Tuesday Jan 28th
Interior shoot: 4pm – 10pm. Civic Centre
Scenes 1 & 3 - Tom & Sean
Remember: collect Surgical scrubs from Mater Hospital in the afternoon

Wednesday Jan 29th 
No shoot

Thursday Jan 30th  
No shoot
Pick up memorial plaque from printers

Friday Jan 31st & Saturday Feb 1st
Exterior shoot: 10am – 3pm. St Anne’s Park
Scenes 2 & 4 - Tom & Geraldine on bench plus shots of Tom walking
           
Sunday Feb 2nd
pick-ups: St Anne’s Park 9am – 11am.

Order subject to change and weather conditions 

*Update*

Exterior shoot reschedule required due to bad weather
Revised date for all outdoor shots. Sunday Feb 2nd 8.30am - 12.30pm

Script read through with Hugh and Rosemary Friday Jan 31st at 10.30am




Sunday, December 8, 2013

Location scout photos


Location Scout - Production Notes

The area on the ground floor of the Coolock Civic Centre that will be using as our Hospital waiting room for scenes 1 & 3. 

Note: I will ask them if we can use the chairs to form a row that will look more like a hospital waiting room.  We've also clarified shooting outside working hours to ensure no sound spillage.




Pond area of St Annes Park which we plan to use for scenes 2 & 4. 

Note: The bench by the pond would be ideal only that there is a main road right beside it so sound quality would be an issue. 





The bench in a different part of the park which we are considering using as it would be a lot quieter.